REPORT ON THE INSTALLATION OF THE NATIONAL CORS PROTOTYPE MONUMENT

Written by
Dennis A. Hoar
Team Leader
Process Action Team 20

July 2000

This report documents the procedures, materials, and costs involved in the setting of a prototype National CORS (Continuously Operating Reference Station) monument, as directed by the Executive Steering Committee in the Team Charter of Process Action Team 20 (PAT 20). The prototype monument was set to verify the recommendations developed by PAT 20 and to determine if any modifications were required to those recommendations.


[See attached .pdf file for more.]

Attached Files (2)
Comments
There are no comments for this article. Be the first to post a comment.
Name
Email
Security Code Security Code
Related Articles RSS Feed
Generic / Simple Rebar-reinforced Concrete Pillar Design and Pipe Diagram (2 diagrams)
Viewed 9850 times since Fri, Dec 12, 2008
Guidelines for Setting a National CORS Monument (2000)
Viewed 12100 times since Thu, Nov 13, 2008
Concrete Pillar at Platteville, Colorado (diagram)
Viewed 4344 times since Wed, Nov 12, 2008
USGS INVAR Rod Encased in Concrete Pillar in Yellowstone, Wyoming (diagram)
Viewed 25570 times since Mon, Nov 24, 2008
INVAR Rod Encased in Concrete Pillar in Greenland (diagram)
Viewed 4042 times since Mon, Nov 24, 2008
INVAR Rod Encased in Concrete Pillar at Red Butte, Utah (2 diagrams)
Viewed 4695 times since Mon, Nov 24, 2008
Concrete Pillar Monument Overview
Viewed 23659 times since Wed, Apr 14, 2010
MENU

Last modified: Monday, 12-May-2014 00:18:29 UTC